Assessment Year | 1998 |
---|---|
Principal Product | Corrugated Shipping Containers |
NAICS |
n/a
|
SIC | 2653: Corrugated and Solid Fiber Boxes |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
265,000
ft2
|
Annual Production | 54,000
ton
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $343,570 | 8,878,371 |
kWh
|
$0.039 |
Electricity Demand | $28,198 | 18,070 |
kW-mo/yr
|
$1.56 |
Natural Gas | $260,248 | 65,734 |
MMBtu
|
$3.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $112,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $36,801 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,516 | $16,781 |
$7,189
152,989
kWh
|
$327
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,297 | $5,022 |
$4,967
127,491
kWh
|
$330
-
kW-mo/yr
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,712 | $6,927 |
$3,481
89,390
kWh
|
$231
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $785 | $1,137 |
$733
18,757
kWh
|
$52
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,738 | $2,600 |
$13,138
312,720
kWh
|
- | - | $(-2,400.0) | |
06 | 2.2135: Repair and eliminate steam leaks | $23,988 | $2,300 | - | - |
$26,288
-
MMBtu
|
$(-2,300.0) | |
07 | 2.2414: Use waste heat from hot flue gases to preheat | $18,852 | $39,600 | - | - |
$18,852
-
MMBtu
|
- | |
08 | 3.6121: Burn waste paper for heat | $18,145 | $90,000 | - | - |
$18,145
-
MMBtu
|
- | |
09 | 3.4116: Meter recycled water (to reduce sewer charges) | $1,089 | $1,500 | - | - | - | $1,089 | |
10 | 4.812: Apply for investment incentives | $21,947 | $50 | - | - | - | $21,947 | |
TOTAL RECOMMENDED | $112,069 | $165,917 |
$29,508
701,347
kWh
|
$940
-
kW-mo/yr
|
$63,285
-
MMBtu
|
$18,336 | ||
TOTAL IMPLEMENTED | $36,801 | $24,103 |
$12,156
280,480
kWh
|
$657
-
kW-mo/yr
|
$26,288
-
MMBtu
|
$(-2,300.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs