Assessment Year | 1998 |
---|---|
Principal Product | Juice Products |
NAICS |
n/a
|
SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
Sales Range | $10 M to 50M |
# of Employees | 175 |
Plant Area |
142,283
ft2
|
Annual Production | 7,000,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $887,518 | 21,898,300 |
kWh
|
$0.041 |
Electricity Demand | $92,817 | 42,836 |
kW-mo/yr
|
$2.17 |
Natural Gas | $77,385 | 13,863 |
MMBtu
|
$5.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $104,803 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $65,957 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,991 | $5,652 |
$1,820
44,256
kWh
|
$171
-
kW-mo/yr
|
- | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $1,088 | $792 |
$984
24,033
kWh
|
$104
-
kW-mo/yr
|
- | - | |
03 | 2.4133: Use most efficient type of electric motors | $4,777 | $4,604 |
$4,400
107,268
kWh
|
$377
-
kW-mo/yr
|
- | - | |
04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $980 | $1,000 |
$980
51,290
kWh
|
- | - | - | |
05 | 2.5113: Use direct flame impingement or infrared processing for chamber type heating | $46,067 | $116,000 |
$63,860
1,557,444
kWh
|
$5,755
-
kW-mo/yr
|
$(-23,548.0)
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $16,919 | $1,200 |
$16,919
376,026
kWh
|
- | - | - | |
07 | 3.6192: Use a less expensive method of waste removal | $1,380 | - | - | - | - | $1,380 | |
08 | 3.1291: Eliminate practice of mixing waste streams | $28,601 | $2,500 | - | - | - | $28,601 | |
09 | 4.111: Add equipment/ operators to reduce production bottleneck | $3,000 | $4,000 | - | - | - | $3,000 | |
TOTAL RECOMMENDED | $104,803 | $135,748 |
$88,963
2,160,317
kWh
|
$6,407
-
kW-mo/yr
|
$(-23,548.0)
-
MMBtu
|
$32,981 | ||
TOTAL IMPLEMENTED | $65,957 | $123,852 |
$83,579
2,029,016
kWh
|
$5,926
-
kW-mo/yr
|
$(-23,548.0)
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs