Assessment Year | 1998 |
---|---|
Principal Product | Paper Foil Labels |
NAICS |
n/a
|
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
80,000
ft2
|
Annual Production | 162,389
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Florida |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $166,903 | 3,096,718 |
kWh
|
$0.054 |
Electricity Demand | $28,565 | 6,634 |
kW-mo/yr
|
$4.31 |
Natural Gas | $229,658 | 38,305 |
MMBtu
|
$6.00 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $82,224 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,667 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,796 | $7,894 |
$2,439
45,135
kWh
|
$357
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,859 | $1,286 |
$1,656
30,774
kWh
|
$203
-
kW-mo/yr
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $2,359 | $882 |
$2,030
37,515
kWh
|
$329
-
kW-mo/yr
|
- | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,910 | $1,350 |
$2,910
46,307
kWh
|
- | - | |
05 | 3.7137: Replace cloth rags with paper towels | $5,530 | - | - | - | $5,530 | |
06 | 3.8132: Use less toxic and volatile solvent substitutes | $42,668 | - | - | - | $42,668 | |
07 | 2.8121: Apply for tax-free status for energy purchases | $11,602 | $750 | - | - | $11,602 | |
08 | 4.321: Optimize production lot sizes and inventories | $12,500 | $6,000 | - | - | $12,500 | |
TOTAL RECOMMENDED | $82,224 | $18,162 |
$9,035
159,731
kWh
|
$889
-
kW-mo/yr
|
$72,300 | ||
TOTAL IMPLEMENTED | $19,667 | $10,876 |
$7,379
128,957
kWh
|
$686
-
kW-mo/yr
|
$11,602 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs