| Assessment Year | 1994 |
|---|---|
| Principal Product | Corrugated boxes and sheets |
| NAICS |
n/a
|
| SIC | 2653: Corrugated and Solid Fiber Boxes |
| Sales Range | $10 M to 50M |
| # of Employees | 125 |
| Plant Area |
194,000
ft2
|
| Annual Production | 504,000,000
pieces
|
| Production Hrs. Annual | 4,992
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $240,181 | 3,356,389 |
kWh
|
$0.072 |
| Natural Gas | $137,064 | 32,412 |
MMBtu
|
$4.23 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $32,444 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,647 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,091 | $3,937 |
$3,091
42,790
kWh
|
- | |
| 02 | 2.7144: Install spectral reflectors / delamp | $2,567 | $3,210 |
$2,567
33,705
kWh
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $4,105 | $4,519 |
$4,105
57,151
kWh
|
- | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,382 | $1,000 |
$1,382
19,050
kWh
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $4,781 | $1,000 | - |
$4,781
-
MMBtu
|
|
| 06 | 2.2414: Use waste heat from hot flue gases to preheat | $3,774 | $2,600 | - |
$3,774
-
MMBtu
|
|
| 07 | 2.2136: Install / repair insulation on steam lines | $851 | $610 | - |
$851
-
MMBtu
|
|
| 08 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,223 | $23,300 |
$10,223
173,212
kWh
|
- | |
| 09 | 2.2135: Repair and eliminate steam leaks | $1,670 | $220 | - |
$1,670
-
MMBtu
|
|
| TOTAL RECOMMENDED | $32,444 | $40,396 |
$21,368
325,908
kWh
|
$11,076
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,647 | $9,676 |
$7,196
99,941
kWh
|
$6,451
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs