ITAC Assessment: UD1073
ITAC logo
ITAC Assessment: UD1073
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Treated Drinking Water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 262,000
ft2
Annual Production 2,153,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $156,918 3,082,586
kWh
Electricity Demand $43,995 6,640
kW-mo/yr
Electricity Fees $552 -
Natural Gas $17,304 1,519
MMBtu
Other Gas $2,574 1
MMBtu
TOTAL YEARLY COSTS $221,343
RECOMMENDED SAVINGS* $54,926 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $28,093

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings
01 2.7241: Install outside air damper / economizer on hvac unit $311 $204 $311
6,119
kWh
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $27,782 $120,000 $27,782
545,808
kWh
03 2.9114: Use solar heat to make electricty $26,833 $247,333 $26,833
527,162
kWh
TOTAL RECOMMENDED $54,926 $367,537 $54,926
1,079,089
kWh
TOTAL IMPLEMENTED $28,093 $120,204 $28,093
551,927
kWh
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs