| Assessment Year | 2019 |
|---|---|
| Principal Product | Canned Tomatoes |
| NAICS | 311421: Fruit and Vegetable Canning |
| SIC | 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies |
| Sales Range | $50 M to 100M |
| # of Employees | 70 |
| Plant Area |
420,000
ft2
|
| Annual Production | 40,000
ton
|
| Production Hrs. Annual | 2,760
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $141,362 | 1,978,200 |
kWh
|
$0.071 | |
| Electricity Demand | $2,448 | 651 |
kW-mo/yr
|
$3.76 | |
| Electricity Fees | $127,211 | - |
|
- | |
| Natural Gas | $183,646 | 43,168 |
MMBtu
|
$4.25 | |
| Waste Disposal Costs | |||||
| Water Usage | $39,891 | 5,637 |
Tgal
|
$7.08 | |
| TOTAL YEARLY COSTS | $494,558 | ||||
| RECOMMENDED SAVINGS* | $60,941 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $22,103 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.6212: Turn off equipment during breaks, reduce operating time | $3,598 | $500 |
$3,598
50,355
kWh
|
- | - | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $299 | - |
$153
2,141
kWh
|
$146
-
kW-mo/yr
|
- | - | |
| 03 | 2.2612: Use cooling tower water instead of refrigeration | $7,123 | $5,000 |
$5,748
80,438
kWh
|
$1,375
-
kW-mo/yr
|
- | - | |
| 04 | 2.2427: Use waste heat from hot flue gases to preheat incoming fluids | $21,830 | $20,000 | - | - |
$21,830
-
MMBtu
|
- | |
| 05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $14,001 | $60,000 | - | - |
$7,251
-
MMBtu
|
$6,750 | |
| 06 | 2.2113: Repair or replace steam traps | $483 | $5,500 | - | - |
$483
-
MMBtu
|
- | |
| 07 | 2.4133: Use most efficient type of electric motors | $4,616 | $7,457 |
$3,899
54,561
kWh
|
$717
-
kW-mo/yr
|
- | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,704 | $10,753 |
$3,071
42,977
kWh
|
$635
-
kW-mo/yr
|
- | $(-2.0) | |
| 09 | 2.7124: Make a practice of turning off lights when not needed | $1,565 | - |
$1,282
17,940
kWh
|
$196
-
kW-mo/yr
|
- | $87 | |
| 10 | 2.5194: Redesign process | $3,722 | $43,500 |
$1,278
17,891
kWh
|
$272
-
kW-mo/yr
|
$2,172
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $60,941 | $152,710 |
$19,029
266,303
kWh
|
$3,341
-
kW-mo/yr
|
$31,736
-
MMBtu
|
$6,835 | ||
| TOTAL IMPLEMENTED | $22,103 | $109,500 |
$5,029
70,387
kWh
|
$418
-
kW-mo/yr
|
$9,906
-
MMBtu
|
$6,750 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs