ITAC Assessment: UD1010
ITAC logo
ITAC Assessment: UD1010
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2019
Principal Product Canned Tomatoes
NAICS 311421: Fruit and Vegetable Canning
SIC 2033: Canned Fruits, Vegetables, Preserves, Jams, and Jellies
Sales Range $50
M
to 100
M
# of Employees 70
Plant Area 420,000
ft2
Annual Production 40,000
ton
Production Hrs. Annual 2,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $141,362 1,978,200
kWh
Electricity Demand $2,448 651
kW-mo/yr
Electricity Fees $127,211 -
Natural Gas $183,646 43,168
MMBtu
Waste Disposal Costs
Water Usage $39,891 5,637
Tgal
TOTAL YEARLY COSTS $494,558
RECOMMENDED SAVINGS* $60,941 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,103

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.6212: Turn off equipment during breaks, reduce operating time $3,598 $500 $3,598
50,355
kWh
- - -
02 2.4231: Reduce the pressure of compressed air to the minimum required $299 - $153
2,141
kWh
$146
-
kW-mo/yr
- -
03 2.2612: Use cooling tower water instead of refrigeration $7,123 $5,000 $5,748
80,438
kWh
$1,375
-
kW-mo/yr
- -
04 2.2427: Use waste heat from hot flue gases to preheat incoming fluids $21,830 $20,000 - - $21,830
-
MMBtu
-
05 2.1233: Analyze flue gas for proper air/fuel ratio $14,001 $60,000 - - $7,251
-
MMBtu
$6,750
06 2.2113: Repair or replace steam traps $483 $5,500 - - $483
-
MMBtu
-
07 2.4133: Use most efficient type of electric motors $4,616 $7,457 $3,899
54,561
kWh
$717
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,704 $10,753 $3,071
42,977
kWh
$635
-
kW-mo/yr
- $(-2.0)
09 2.7124: Make a practice of turning off lights when not needed $1,565 - $1,282
17,940
kWh
$196
-
kW-mo/yr
- $87
10 2.5194: Redesign process $3,722 $43,500 $1,278
17,891
kWh
$272
-
kW-mo/yr
$2,172
-
MMBtu
-
TOTAL RECOMMENDED $60,941 $152,710 $19,029
266,303
kWh
$3,341
-
kW-mo/yr
$31,736
-
MMBtu
$6,835
TOTAL IMPLEMENTED $22,103 $109,500 $5,029
70,387
kWh
$418
-
kW-mo/yr
$9,906
-
MMBtu
$6,750
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs