| Assessment Year | 2019 |
|---|---|
| Principal Product | Automotive Fasteners |
| NAICS | 332721: Precision Turned Product Manufacturing |
| SIC | 3451: Screw Machine Products |
| Sales Range | $1 M to 5M |
| # of Employees | 23 |
| Plant Area |
44,750
ft2
|
| Annual Production | 3,000,000
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $39,926 | 596,077 |
kWh
|
$0.067 | |
| Electricity Demand | $7,730 | 2,112 |
kW-mo/yr
|
$3.66 | |
| Electricity Fees | $309 | - |
|
- | |
| Natural Gas | $18,486 | 2,483 |
MMBtu
|
$7.45 | |
| Waste Disposal Costs | |||||
| Water Usage | $1,106 | 99 |
Tgal
|
$11.12 | |
| Water Disposal | $3,673 | 99 |
Tgal
|
$36.92 | |
| TOTAL YEARLY COSTS | $71,230 | ||||
| RECOMMENDED SAVINGS* | $17,487 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $17,487 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,285 | $4,400 |
$2,825
41,852
kWh
|
$460
-
kW-mo/yr
|
- | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $705 | $1,200 |
$916
13,565
kWh
|
$149
-
kW-mo/yr
|
$(-360.0) | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,497 | $16,508 |
$11,056
163,720
kWh
|
$1,796
-
kW-mo/yr
|
$645 | |
| TOTAL RECOMMENDED | $17,487 | $22,108 |
$14,797
219,137
kWh
|
$2,405
-
kW-mo/yr
|
$285 | ||
| TOTAL IMPLEMENTED | $17,487 | $22,108 |
$14,797
219,137
kWh
|
$2,405
-
kW-mo/yr
|
$285 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs