| Assessment Year | 2002 |
|---|---|
| Principal Product | automotive stampings |
| NAICS |
n/a
|
| SIC | 3465: Automotive Stampings |
| Sales Range | $10 M to 50M |
| # of Employees | 112 |
| Plant Area |
144,000
ft2
|
| Annual Production | 16,000,000
lb
|
| Production Hrs. Annual | 6,500
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $149,284 | 4,829,857 |
kWh
|
$0.031 |
| Electricity Demand | $99,522 | 11,916 |
kW-mo/yr
|
$8.35 |
| Natural Gas | $36,764 | 5,167 |
MMBtu
|
$7.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $1,005,204 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $990,180 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.621: Use fixtures to reduce machine changeout times | $962,280 | $448,000 | - | - | - | - | $962,280 | |
| 02 | 3.4111: Use closed cycle process to minimize waste water production | $20,837 | $16,100 | - | - | - |
$20,837
-
Tgal
|
- | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,063 | $8,000 |
$4,056
156,000
kWh
|
$3,007
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $5,863 | $1,050 |
$2,355
208,366
kWh
|
$3,508
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7231: Use radiant heater for spot heating | $4,586 | $7,938 | - | - |
$4,586
-
MMBtu
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,826 | $8,905 |
$2,197
84,500
kWh
|
$1,629
-
kW-mo/yr
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $749 | - |
$749
28,800
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $1,005,204 | $489,993 |
$9,357
477,666
kWh
|
$8,144
-
kW-mo/yr
|
$4,586
-
MMBtu
|
$20,837
-
Tgal
|
$962,280 | ||
| TOTAL IMPLEMENTED | $990,180 | $472,100 |
$4,056
156,000
kWh
|
$3,007
-
kW-mo/yr
|
- |
$20,837
-
Tgal
|
$962,280 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Consumption Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs