ITAC Assessment: UD0636
ITAC logo
ITAC Assessment: UD0636
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Acid proof ceramics, Steel liners and packing
NAICS
n/a
SIC 3259: Structural Clay Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 91
Plant Area 36,000
ft2
Annual Production 5,100
ton
Production Hrs. Annual 7,488
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,997 2,102,480
kWh
Electricity Demand $21,548 6,264
kW-mo/yr
Natural Gas $557,323 96,646
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,922 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $118,922

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
01 3.2176: Increase use of automation $62,400 - - - - - $62,400 -
02 2.2511: Insulate bare equipment $20,587 $7,200 - - - $20,587
-
MMBtu
- -
03 2.2414: Use waste heat from hot flue gases to preheat $20,230 $25,000 - - - $20,230
-
MMBtu
- -
04 2.3212: Optimize plant power factor $4,987 $3,750 - - $4,987 - - -
05 2.1233: Analyze flue gas for proper air/fuel ratio $4,247 $500 - - - $4,247
-
MMBtu
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,668 $1,185 $610
14,196
kWh
$188
-
kW-mo/yr
- - - $870
07 2.7142: Utilize higher efficiency lamps and/or ballasts $1,509 $2,880 $1,154
26,832
kWh
$355
-
kW-mo/yr
- - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,335 $420 $815
18,953
kWh
$520
-
kW-mo/yr
- - - -
09 2.2424: Use heat in flue gases to preheat products or materials $1,223 - - - - $1,223
-
MMBtu
- -
10 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $736 $300 $563
13,104
kWh
$173
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $118,922 $41,235 $3,142
73,085
kWh
$1,236
-
kW-mo/yr
$4,987 $46,287
-
MMBtu
$62,400 $870
TOTAL IMPLEMENTED $118,922 $41,235 $3,142
73,085
kWh
$1,236
-
kW-mo/yr
$4,987 $46,287
-
MMBtu
$62,400 $870
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs