ITAC Assessment: UD0593
ITAC logo
ITAC Assessment: UD0593
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product gray and ductile iron castings, fabricated metal
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 350
Plant Area 400,000
ft2
Annual Production 84,000,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $845,115 22,220,985
kWh
Electricity Demand $91,820 30,144
kW-mo/yr
Natural Gas $139,337 34,665
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $159,172 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $45,511

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Other Energy Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.8114: Change rate schedules or other changes in utility service $75,117 - - - - - $75,117 -
02 3.1191: Change procedures / equipment / operating conditions $42,268 $45,000 - - $768
-
MMBtu
$34,000 - $7,500
03 2.1392: Replace purchased steam with other energy source $36,834 $55,945 - $(-45,969.0)
-
MMBtu
$82,803
-
MMBtu
- - -
04 2.2136: Install / repair insulation on steam lines $3,243 $6,080 - - $3,243
-
MMBtu
- - -
05 2.7121: Utilize daylight whenever possible in lieu of artificial light $1,710 - $1,710
45,135
kWh
- - - - -
TOTAL RECOMMENDED $159,172 $107,025 $1,710
45,135
kWh
$(-45,969.0)
-
MMBtu
$86,814
-
MMBtu
$34,000 $75,117 $7,500
TOTAL IMPLEMENTED $45,511 $51,080 - - $4,011
-
MMBtu
$34,000 - $7,500
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs