| Assessment Year | 2000 |
|---|---|
| Principal Product | gray and ductile iron castings, fabricated metal |
| NAICS |
n/a
|
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 350 |
| Plant Area |
400,000
ft2
|
| Annual Production | 84,000,000
lb
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $845,115 | 22,220,985 |
kWh
|
$0.038 |
| Electricity Demand | $91,820 | 30,144 |
kW-mo/yr
|
$3.05 |
| Natural Gas | $139,337 | 34,665 |
MMBtu
|
$4.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $159,172 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,511 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Energy Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8114: Change rate schedules or other changes in utility service | $75,117 | - | - | - | - | - | $75,117 | - | |
| 02 | 3.1191: Change procedures / equipment / operating conditions | $42,268 | $45,000 | - | - |
$768
-
MMBtu
|
$34,000 | - | $7,500 | |
| 03 | 2.1392: Replace purchased steam with other energy source | $36,834 | $55,945 | - |
$(-45,969.0)
-
MMBtu
|
$82,803
-
MMBtu
|
- | - | - | |
| 04 | 2.2136: Install / repair insulation on steam lines | $3,243 | $6,080 | - | - |
$3,243
-
MMBtu
|
- | - | - | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $1,710 | - |
$1,710
45,135
kWh
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $159,172 | $107,025 |
$1,710
45,135
kWh
|
$(-45,969.0)
-
MMBtu
|
$86,814
-
MMBtu
|
$34,000 | $75,117 | $7,500 | ||
| TOTAL IMPLEMENTED | $45,511 | $51,080 | - | - |
$4,011
-
MMBtu
|
$34,000 | - | $7,500 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs