ITAC Assessment: UD0453
ITAC logo
ITAC Assessment: UD0453
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product swivels, loader arms, visi-flo
NAICS
n/a
SIC 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 38,000
ft2
Annual Production 0
units
Production Hrs. Annual 6,300
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,331 914,420
kWh
Natural Gas $5,346 909
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,811 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,640

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,324 $250 $4,324
-
kWh
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $5,640 - $5,640
-
kWh
-
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $656 $5,000 $656
30,188
kWh
-
04 2.2437: Recover waste heat from equipment $894 $2,000 - $894
-
MMBtu
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,297 $2,880 $1,297
19,050
kWh
-
TOTAL RECOMMENDED $12,811 $10,130 $11,917
49,238
kWh
$894
-
MMBtu
TOTAL IMPLEMENTED $5,640 - $5,640
-
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs