| Assessment Year | 1995 |
|---|---|
| Principal Product | swivels, loader arms, visi-flo |
| NAICS |
n/a
|
| SIC | 3568: Mechanical Power Transmission Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
38,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $57,331 | 914,420 |
kWh
|
$0.063 |
| Natural Gas | $5,346 | 909 |
MMBtu
|
$5.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $12,811 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $5,640 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,324 | $250 |
$4,324
-
kWh
|
- | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,640 | - |
$5,640
-
kWh
|
- | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $656 | $5,000 |
$656
30,188
kWh
|
- | |
| 04 | 2.2437: Recover waste heat from equipment | $894 | $2,000 | - |
$894
-
MMBtu
|
|
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,297 | $2,880 |
$1,297
19,050
kWh
|
- | |
| TOTAL RECOMMENDED | $12,811 | $10,130 |
$11,917
49,238
kWh
|
$894
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $5,640 | - |
$5,640
-
kWh
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs