Assessment Year | 1994 |
---|---|
Principal Product | elevators and escalators |
NAICS |
n/a
|
SIC | 3534: Elevators and Moving Stairways |
Sales Range | $10 M to 50M |
# of Employees | 325 |
Plant Area |
240,000
ft2
|
Annual Production | 78
pieces
|
Production Hrs. Annual | 3,600
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $244,766 | 4,033,998 |
kWh
|
$0.061 |
Natural Gas | $86,920 | 15,454 |
MMBtu
|
$5.62 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $30,824 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $7,448 | - | n/a |
$7,448
389,801
kWh
|
- |
02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,640 | $250 | n/a |
$8,640
-
kWh
|
- |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,786 | $3,000 | n/a |
$8,454
147,714
kWh
|
$2,332
-
MMBtu
|
04 | 2.7131: Add area lighting switches | $2,496 | $200 | n/a |
$2,496
43,669
kWh
|
- |
05 | 2.7131: Add area lighting switches | $1,454 | $200 | n/a |
$1,454
29,015
kWh
|
- |
TOTAL RECOMMENDED | $30,824 | $3,650 |
$28,492
610,199
kWh
|
$2,332
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs