| Assessment Year | 1994 |
|---|---|
| Principal Product | elevators and escalators |
| NAICS |
n/a
|
| SIC | 3534: Elevators and Moving Stairways |
| Sales Range | $10 M to 50M |
| # of Employees | 325 |
| Plant Area |
240,000
ft2
|
| Annual Production | 78
pieces
|
| Production Hrs. Annual | 3,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $244,766 | 4,033,998 |
kWh
|
$0.061 |
| Natural Gas | $86,920 | 15,454 |
MMBtu
|
$5.62 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $30,824 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7221: Lower temperature during the winter season and vice-versa | $7,448 | - | n/a |
$7,448
389,801
kWh
|
- |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $8,640 | $250 | n/a |
$8,640
-
kWh
|
- |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,786 | $3,000 | n/a |
$8,454
147,714
kWh
|
$2,332
-
MMBtu
|
| 04 | 2.7131: Add area lighting switches | $2,496 | $200 | n/a |
$2,496
43,669
kWh
|
- |
| 05 | 2.7131: Add area lighting switches | $1,454 | $200 | n/a |
$1,454
29,015
kWh
|
- |
| TOTAL RECOMMENDED | $30,824 | $3,650 |
$28,492
610,199
kWh
|
$2,332
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs