| Assessment Year | 1993 |
|---|---|
| Principal Product | Flexible packaging |
| NAICS |
n/a
|
| SIC | 2754: Commercial Printing, Gravure |
| Sales Range | $10 M to 50M |
| # of Employees | 140 |
| Plant Area |
100,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 6,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $297,367 | 4,704,865 |
kWh
|
$0.063 |
| Natural Gas | $210,642 | 40,650 |
MMBtu
|
$5.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $137,056 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $30,517 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $25,572 | $16,000 |
$25,572
-
kWh
|
- | |
| 02 | 2.8113: Purchase gas directly from a contract gas supplier | $64,530 | $13,000 |
$64,530
-
kWh
|
- | |
| 03 | 2.3191: Use demand controller or load shedder | $14,071 | $250 |
$14,071
-
kWh
|
- | |
| 04 | 2.3191: Use demand controller or load shedder | $1,840 | - |
$1,840
-
kWh
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,048 | $2,456 |
$1,048
-
kWh
|
- | |
| 06 | 2.2437: Recover waste heat from equipment | $3,897 | $3,000 | - |
$3,897
-
MMBtu
|
|
| 07 | 2.5195: Change product design to reduce energy requirements | $26,098 | - | - |
$26,098
-
MMBtu
|
|
| TOTAL RECOMMENDED | $137,056 | $34,706 |
$107,061
-
kWh
|
$29,995
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $30,517 | $21,456 |
$26,620
-
kWh
|
$3,897
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs