ITAC Assessment: UD0281
ITAC logo
ITAC Assessment: UD0281
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1989
Principal Product STEEL PLATE PROCESSOR
NAICS
n/a
SIC 3499: Fabricated Metal Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area
n/a
Annual Production 7,000
ton
Production Hrs. Annual 6,300
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $120,150 1,926,436
kWh
Natural Gas $63,931 15,638
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,081 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,651

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.3134: Shift from daytime to nighttime operation $2,368 - $3,200
-
kWh
- $(-832.0)
02 2.3134: Shift from daytime to nighttime operation $6,430 - $6,630
-
kWh
- $(-200.0)
03 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $4,189 $1,500 $3,347
50,703
kWh
$417
-
MMBtu
$425
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,628 $1,350 $2,016
41,325
kWh
$(-388.0)
-
MMBtu
-
05 2.7494: Install storm windows and doors $13,466 $14,758 - $13,466
-
MMBtu
-
TOTAL RECOMMENDED $28,081 $17,608 $15,193
92,028
kWh
$13,495
-
MMBtu
$(-607.0)
TOTAL IMPLEMENTED $21,651 $17,608 $8,563
92,028
kWh
$13,495
-
MMBtu
$(-407.0)
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs