| Assessment Year | 1989 |
|---|---|
| Principal Product | STEEL PLATE PROCESSOR |
| NAICS |
n/a
|
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 85 |
| Plant Area |
n/a
|
| Annual Production | 7,000
ton
|
| Production Hrs. Annual | 6,300
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $120,150 | 1,926,436 |
kWh
|
$0.062 |
| Natural Gas | $63,931 | 15,638 |
MMBtu
|
$4.09 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,081 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $21,651 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3134: Shift from daytime to nighttime operation | $2,368 | - |
$3,200
-
kWh
|
- | $(-832.0) | |
| 02 | 2.3134: Shift from daytime to nighttime operation | $6,430 | - |
$6,630
-
kWh
|
- | $(-200.0) | |
| 03 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $4,189 | $1,500 |
$3,347
50,703
kWh
|
$417
-
MMBtu
|
$425 | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,628 | $1,350 |
$2,016
41,325
kWh
|
$(-388.0)
-
MMBtu
|
- | |
| 05 | 2.7494: Install storm windows and doors | $13,466 | $14,758 | - |
$13,466
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $28,081 | $17,608 |
$15,193
92,028
kWh
|
$13,495
-
MMBtu
|
$(-607.0) | ||
| TOTAL IMPLEMENTED | $21,651 | $17,608 |
$8,563
92,028
kWh
|
$13,495
-
MMBtu
|
$(-407.0) | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs