ITAC Assessment: UD0156
ITAC logo
ITAC Assessment: UD0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product DATA PROCESSING
NAICS
n/a
SIC 2731: Books: Publishing, or Publishing and Printing
Sales Range $5
M
to 10
M
# of Employees 190
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,300
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $53,060 759,086
kWh
Natural Gas $9,323 1,424
MMBtu
Fuel Oil #2 $1,898 228
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $8,160 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,116

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Fuel Oil #2 Savings
01 2.8114: Change rate schedules or other changes in utility service $4,044 $5,000 $4,044
-
kWh
- -
02 2.6121: Reduce hot water temperature to the minimum required $314 - - $314
-
MMBtu
-
03 2.7111: Reduce illumination to minimum necessary levels $319 $130 $382
4,396
kWh
$(-63.0)
-
MMBtu
-
04 2.7226: Use computer programs to optimize hvac performance $3,483 $2,988 - $2,815
-
MMBtu
$668
-
MMBtu
TOTAL RECOMMENDED $8,160 $8,118 $4,426
4,396
kWh
$3,066
-
MMBtu
$668
-
MMBtu
TOTAL IMPLEMENTED $4,116 $3,118 $382
4,396
kWh
$3,066
-
MMBtu
$668
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs