| Assessment Year | 1983 |
|---|---|
| Principal Product | TOOLS THAT LIFT-STRETCH |
| NAICS |
n/a
|
| SIC | 3542: Machine Tools, Metal Forming Types |
| Sales Range | $5 M to 10M |
| # of Employees | 120 |
| Plant Area |
n/a
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 5,400
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $80,885 | 1,456,038 |
kWh
|
$0.056 |
| Natural Gas | $7,619 | 1,689 |
MMBtu
|
$4.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $3,481 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,269 | $548 |
$2,733
51,290
kWh
|
$(-464.0)
-
MMBtu
|
|
| 02 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $1,212 | $1,000 |
$1,504
13,482
kWh
|
$(-292.0)
-
MMBtu
|
|
| TOTAL RECOMMENDED | $3,481 | $1,548 |
$4,237
64,772
kWh
|
$(-756.0)
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs