ITAC Assessment: UD0061
ITAC logo
ITAC Assessment: UD0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product SPECIAL MACHINES
NAICS
n/a
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 117
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 5,700
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $103,591 2,104,338
kWh
Natural Gas $10,614 2,357
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $6,030 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $72

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,961 $9,877 $5,340
107,855
kWh
$(-379.0)
-
MMBtu
02 2.6121: Reduce hot water temperature to the minimum required $72 - - $72
-
MMBtu
03 2.2437: Recover waste heat from equipment $820 $270 $144
2,638
kWh
$676
-
MMBtu
04 2.7233: Use properly designed and sized hvac equipment $177 $500 $177
3,224
kWh
-
TOTAL RECOMMENDED $6,030 $10,647 $5,661
113,717
kWh
$369
-
MMBtu
TOTAL IMPLEMENTED $72 - - $72
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs