Assessment Year | 2017 |
---|---|
Principal Product | Bumpers and Instrumentation Panels |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | greater than $500 M |
# of Employees | 1,092 |
Plant Area |
599,433
ft2
|
Annual Production | 5,421,041
units
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Alabama |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $3,633,731 | 68,170,724 |
kWh
|
$0.053 |
Electricity Demand | $613,281 | 141,578 |
kW-mo/yr
|
$4.33 |
Electricity Fees | $24,004 | - |
|
- |
Natural Gas | $913,530 | 128,744 |
MMBtu
|
$7.10 |
TOTAL YEARLY COSTS | $5,184,546 | |||
RECOMMENDED SAVINGS* | $289,677 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $174,259 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $14,441 | $1,892 |
$11,845
222,234
kWh
|
$2,027
-
kW-mo/yr
|
$569 | - | |
02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $67,895 | $250 |
$55,483
1,040,953
kWh
|
$9,738
-
kW-mo/yr
|
$2,674 | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $38,219 | $6,260 |
$30,944
580,564
kWh
|
$5,770
-
kW-mo/yr
|
$1,505 | - | |
04 | 2.2437: Recover waste heat from equipment | $33,082 | $14,405 | - | - | - |
$33,082
-
MMBtu
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $48,032 | $136,663 |
$39,459
740,317
kWh
|
$6,681
-
kW-mo/yr
|
$1,892 | - | |
06 | 2.7241: Install outside air damper / economizer on hvac unit | $88,008 | - |
$84,542
1,586,153
kWh
|
- | $3,466 | - | |
TOTAL RECOMMENDED | $289,677 | $159,470 |
$222,273
4,170,221
kWh
|
$24,216
-
kW-mo/yr
|
$10,106 |
$33,082
-
MMBtu
|
||
TOTAL IMPLEMENTED | $174,259 | $142,923 |
$154,945
2,907,034
kWh
|
$12,451
-
kW-mo/yr
|
$6,863 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs