Assessment Year | 2023 |
---|---|
Principal Product | Extruder Fibers for use in concrete reinforcement |
NAICS | 325220: Artificial and Synthetic Fibers and Filaments Manufacturing |
SIC | 2824: Manmade Organic Fibers, Except Cellulosic |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
1,000,000
ft2
|
Annual Production | 1,000,000
lb
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | Tennessee |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $394,070 | 7,575,496 |
kWh
|
$0.052 | |
Electricity Demand | $230,657 | 17,532 |
kW-mo/yr
|
$13.16 | |
Natural Gas | $7,145 | 499 |
MMBtu
|
$14.32 | |
Waste Disposal Costs | |||||
Water Usage | $15,373 | 896 |
Tgal
|
$17.16 | |
TOTAL YEARLY COSTS | $647,245 | ||||
RECOMMENDED SAVINGS* | $107,323 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $87,336 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.8121: Apply for tax-free status for energy purchases | $39,135 | - | - | - | $39,135 | |
02 | 2.2625: Chill water to the highest temperature possible | $33,678 | $1,200 |
$33,678
647,400
kWh
|
- | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $896 | $100 |
$896
17,231
kWh
|
- | - | |
04 | 2.2511: Insulate bare equipment | $11,430 | $3,000 |
$11,430
219,715
kWh
|
- | - | |
05 | 2.2437: Recover waste heat from equipment | $1,790 | $1,500 | - |
$1,790
-
MMBtu
|
- | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,197 | $2,025 |
$2,197
42,239
kWh
|
- | - | |
07 | 2.6212: Turn off equipment during breaks, reduce operating time | $582 | $800 |
$582
11,190
kWh
|
- | - | |
08 | 2.4239: Eliminate or reduce compressed air usage | $1,028 | $2,000 |
$1,028
19,757
kWh
|
- | - | |
09 | 2.9114: Use solar heat to make electricty | $16,587 | $75,228 |
$16,587
318,866
kWh
|
- | - | |
TOTAL RECOMMENDED | $107,323 | $85,853 |
$66,398
1,276,398
kWh
|
$1,790
-
MMBtu
|
$39,135 | ||
TOTAL IMPLEMENTED | $87,336 | $6,325 |
$48,201
926,585
kWh
|
- | $39,135 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs