ITAC Assessment: TT0061
ITAC logo
ITAC Assessment: TT0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Sprouting Products and Sprouts
NAICS 333241: Food Product Machinery Manufacturing
SIC 3556: Food Products Machinery
Sales Range $1
M
to 5
M
# of Employees 35
Plant Area 58,500
ft2
Annual Production 2,064,000
lb
Production Hrs. Annual 3,800
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $42,422 701,480
kWh
Electricity Demand $20,423 2,012
kW-mo/yr
Electricity Fees $4,309 -
Natural Gas $29,328 2,716
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,708 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,708

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,100 $4,800 $1,200
20,292
kWh
$900
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $195 - $150
2,287
kWh
$45
-
kW-mo/yr
-
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $513 $1,200 $313
5,391
kWh
$200
-
kW-mo/yr
-
04 2.8121: Apply for tax-free status for energy purchases $4,900 - - - $4,900
TOTAL RECOMMENDED $7,708 $6,000 $1,663
27,970
kWh
$1,145
-
kW-mo/yr
$4,900
TOTAL IMPLEMENTED $7,708 $6,000 $1,663
27,970
kWh
$1,145
-
kW-mo/yr
$4,900
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs