| Assessment Year | 2007 |
|---|---|
| Principal Product | plating |
| NAICS | 332813: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
| Sales Range | $1 M to 5M |
| # of Employees | 9 |
| Plant Area |
5,000
ft2
|
| Annual Production | 7,200,000
pieces
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $12,148 | 154,920 |
kWh
|
$0.078 |
| Electricity Demand | $1,685 | 735 |
kW-mo/yr
|
$2.29 |
| Electricity Fees | $338 | - |
|
- |
| Natural Gas | $48,502 | 3,341 |
MMBtu
|
$14.52 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $23,590 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $23,033 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2136: Install / repair insulation on steam lines | $20,486 | $2,500 | - |
$20,486
-
MMBtu
|
|
| 02 | 2.2123: Insulate feedwater tank | $654 | $500 | - |
$654
-
MMBtu
|
|
| 03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $1,491 | - | - |
$1,491
-
MMBtu
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $402 | - |
$402
49,609
kWh
|
- | |
| 05 | 2.2113: Repair or replace steam traps | $557 | - |
$557
13,711
kWh
|
- | |
| TOTAL RECOMMENDED | $23,590 | $3,000 |
$959
63,320
kWh
|
$22,631
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $23,033 | $3,000 |
$402
49,609
kWh
|
$22,631
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs