Assessment Year | 2000 |
---|---|
Principal Product | Jet Fuel testing equipment |
NAICS |
n/a
|
SIC | 3724: Aircraft Engines and Engine Parts |
Sales Range | $1 M to 5M |
# of Employees | 56 |
Plant Area |
n/a
|
Annual Production | 65,000
pieces
|
Production Hrs. Annual | 2,125
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $24,643 | 662,368 |
kWh
|
$0.037 |
Electricity Demand | $13,375 | 1,992 |
kW-mo/yr
|
$6.71 |
Natural Gas | $667 | 148 |
MMBtu
|
$4.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $57,638 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.522: Modify storage space to avoid rental of a warehouse | $52,800 | $48,300 | - | - | - | $52,800 | - | |
02 | 3.7124: Install dedicated mixing equip to optimize reuse of used rinseate & to preclude the need for inter-run cleaning | $3,716 | $2,056 | - | - |
$3,716
-
gal
|
- | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $843 | $700 |
$107
3,517
kWh
|
$33
-
kW-mo/yr
|
- | - | $703 | |
04 | 2.7135: Install occupancy sensors | $279 | $847 |
$279
8,792
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $57,638 | $51,903 |
$386
12,309
kWh
|
$33
-
kW-mo/yr
|
$3,716
-
gal
|
$52,800 | $703 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs