ITAC Assessment: TP0018
ITAC logo
ITAC Assessment: TP0018
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Jet Fuel testing equipment
NAICS
n/a
SIC 3724: Aircraft Engines and Engine Parts
Sales Range $1
M
to 5
M
# of Employees 56
Plant Area
n/a
Annual Production 65,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $24,643 662,368
kWh
Electricity Demand $13,375 1,992
kW-mo/yr
Natural Gas $667 148
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $57,638 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Administrative Changes Savings Ancillary Material Cost Savings
01 4.522: Modify storage space to avoid rental of a warehouse $52,800 $48,300 - - - $52,800 -
02 3.7124: Install dedicated mixing equip to optimize reuse of used rinseate & to preclude the need for inter-run cleaning $3,716 $2,056 - - $3,716
-
gal
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $843 $700 $107
3,517
kWh
$33
-
kW-mo/yr
- - $703
04 2.7135: Install occupancy sensors $279 $847 $279
8,792
kWh
- - - -
TOTAL RECOMMENDED $57,638 $51,903 $386
12,309
kWh
$33
-
kW-mo/yr
$3,716
-
gal
$52,800 $703
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs