| Assessment Year | 2000 |
|---|---|
| Principal Product | Jet Fuel testing equipment |
| NAICS |
n/a
|
| SIC | 3724: Aircraft Engines and Engine Parts |
| Sales Range | $1 M to 5M |
| # of Employees | 56 |
| Plant Area |
n/a
|
| Annual Production | 65,000
pieces
|
| Production Hrs. Annual | 2,125
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $24,643 | 662,368 |
kWh
|
$0.037 |
| Electricity Demand | $13,375 | 1,992 |
kW-mo/yr
|
$6.71 |
| Natural Gas | $667 | 148 |
MMBtu
|
$4.51 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $57,638 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.522: Modify storage space to avoid rental of a warehouse | $52,800 | $48,300 | - | - | - | $52,800 | - | |
| 02 | 3.7124: Install dedicated mixing equip to optimize reuse of used rinseate & to preclude the need for inter-run cleaning | $3,716 | $2,056 | - | - |
$3,716
-
gal
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $843 | $700 |
$107
3,517
kWh
|
$33
-
kW-mo/yr
|
- | - | $703 | |
| 04 | 2.7135: Install occupancy sensors | $279 | $847 |
$279
8,792
kWh
|
- | - | - | - | |
| TOTAL RECOMMENDED | $57,638 | $51,903 |
$386
12,309
kWh
|
$33
-
kW-mo/yr
|
$3,716
-
gal
|
$52,800 | $703 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs