Assessment Year | 1999 |
---|---|
Principal Product | Railcar manufacturing and repair |
NAICS |
n/a
|
SIC | 3743: Railroad Equipment |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 1,225
pieces
|
Production Hrs. Annual | 4,267
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $116,486 | 2,046,600 |
kWh
|
$0.057 |
Electricity Demand | $428,178 | 60,222 |
kW-mo/yr
|
$7.11 |
Electricity Fees | $35,747 | - |
|
- |
Natural Gas | $591,014 | 255,805 |
MMBtu
|
$2.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $106,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,189 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7124: Make a practice of turning off lights when not needed | $24,189 | $1,848 |
$24,189
806,272
kWh
|
- | |
02 | 2.3212: Optimize plant power factor | $33,041 | $51,500 | - |
$33,041
-
kW-mo/yr
|
|
03 | 2.7124: Make a practice of turning off lights when not needed | $36,820 | $1,728 |
$20,230
674,385
kWh
|
$16,590
-
kW-mo/yr
|
|
04 | 2.7124: Make a practice of turning off lights when not needed | $7,545 | $2,000 |
$4,818
160,610
kWh
|
$2,727
-
kW-mo/yr
|
|
05 | 2.4133: Use most efficient type of electric motors | $3,456 | $35,097 |
$1,715
57,151
kWh
|
$1,741
-
kW-mo/yr
|
|
06 | 2.4314: Use synthetic lubricant | $1,248 | - |
$652
21,688
kWh
|
$596
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $106,299 | $92,173 |
$51,604
1,720,106
kWh
|
$54,695
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $24,189 | $1,848 |
$24,189
806,272
kWh
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs