ITAC Assessment: TN0354
ITAC logo
ITAC Assessment: TN0354
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1988
Principal Product CAST IRON SOIL PIPE
NAICS
n/a
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 313
Plant Area
n/a
Annual Production 42,000
ton
Production Hrs. Annual 6,000
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $774,036 12,337,632
kWh
Natural Gas $418,718 93,812
MMBtu
Coal $795,335 162,891
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $109,560 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $79,554

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Coal Savings
01 2.7231: Use radiant heater for spot heating $61,495 $24,325 - $21,747
-
MMBtu
$39,748
-
MMBtu
02 2.1122: Re-size charging openings or add a movable door on equipment $19,453 $41,240 - $4,349
-
MMBtu
$15,104
-
MMBtu
03 2.2428: Use flue gases in radiant heater for space heating, ovens, etc $8,122 $24,320 - $8,122
-
MMBtu
-
04 2.2531: Re-size charging openings or add movable cover or door $3,459 $13,400 - - $3,459
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $9,509 $540 $9,509
151,524
kWh
- -
06 2.4312: Improve lubrication practices $7,094 $3,190 $7,094
113,130
kWh
- -
07 2.2511: Insulate bare equipment $428 $75 - $428
-
MMBtu
-
TOTAL RECOMMENDED $109,560 $107,090 $16,603
264,654
kWh
$34,646
-
MMBtu
$58,311
-
MMBtu
TOTAL IMPLEMENTED $79,554 $49,260 $9,509
151,524
kWh
$30,297
-
MMBtu
$39,748
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Coal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs