| Assessment Year | 1988 |
|---|---|
| Principal Product | CAST IRON SOIL PIPE |
| NAICS |
n/a
|
| SIC | 3321: Gray and Ductile Iron Foundries |
| Sales Range | $10 M to 50M |
| # of Employees | 313 |
| Plant Area |
n/a
|
| Annual Production | 42,000
ton
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $774,036 | 12,337,632 |
kWh
|
$0.063 |
| Natural Gas | $418,718 | 93,812 |
MMBtu
|
$4.46 |
| Coal | $795,335 | 162,891 |
MMBtu
|
$4.88 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $109,560 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $79,554 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Coal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7231: Use radiant heater for spot heating | $61,495 | $24,325 | - |
$21,747
-
MMBtu
|
$39,748
-
MMBtu
|
|
| 02 | 2.1122: Re-size charging openings or add a movable door on equipment | $19,453 | $41,240 | - |
$4,349
-
MMBtu
|
$15,104
-
MMBtu
|
|
| 03 | 2.2428: Use flue gases in radiant heater for space heating, ovens, etc | $8,122 | $24,320 | - |
$8,122
-
MMBtu
|
- | |
| 04 | 2.2531: Re-size charging openings or add movable cover or door | $3,459 | $13,400 | - | - |
$3,459
-
MMBtu
|
|
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,509 | $540 |
$9,509
151,524
kWh
|
- | - | |
| 06 | 2.4312: Improve lubrication practices | $7,094 | $3,190 |
$7,094
113,130
kWh
|
- | - | |
| 07 | 2.2511: Insulate bare equipment | $428 | $75 | - |
$428
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $109,560 | $107,090 |
$16,603
264,654
kWh
|
$34,646
-
MMBtu
|
$58,311
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $79,554 | $49,260 |
$9,509
151,524
kWh
|
$30,297
-
MMBtu
|
$39,748
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Coal Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs