ITAC Assessment: TN0307
ITAC logo
ITAC Assessment: TN0307
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1987
Principal Product PRECOOKED FROZEN FOODS
NAICS
n/a
SIC 2053: Frozen Bakery Products, Except Bread
Sales Range $10
M
to 50
M
# of Employees 200
Plant Area
n/a
Annual Production 23,400,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $503,928 10,443,728
kWh
Natural Gas $168,407 37,422
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $44,242 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $18,970

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
01 2.2437: Recover waste heat from equipment $25,272 $53,800 - $25,272
-
MMBtu
-
02 2.1233: Analyze flue gas for proper air/fuel ratio $2,495 - - $3,695
-
MMBtu
$(-1,200.0)
03 2.2515: Use optimum thickness insulation $2,858 $2,841 - $2,858
-
MMBtu
-
04 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $8,300 $1,860 $8,300
172,919
kWh
- -
05 2.2163: Use minimum steam operating pressure $2,457 $3,100 - $2,457
-
MMBtu
-
06 2.2136: Install / repair insulation on steam lines $1,211 $176 - $1,211
-
MMBtu
-
07 2.4231: Reduce the pressure of compressed air to the minimum required $1,505 - $1,505
31,360
kWh
- -
08 2.2511: Insulate bare equipment $144 $66 - $144
-
MMBtu
-
TOTAL RECOMMENDED $44,242 $61,843 $9,805
204,279
kWh
$35,637
-
MMBtu
$(-1,200.0)
TOTAL IMPLEMENTED $18,970 $8,043 $9,805
204,279
kWh
$10,365
-
MMBtu
$(-1,200.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs