| Assessment Year | 1985 |
|---|---|
| Principal Product | CANDY |
| NAICS |
n/a
|
| SIC | 2064: Candy and Other Confectionery Products |
| Sales Range | $10 M to 50M |
| # of Employees | 498 |
| Plant Area |
n/a
|
| Annual Production | 41,000,000
lb
|
| Production Hrs. Annual | 6,120
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $499,073 | 11,470,106 |
kWh
|
$0.044 |
| Natural Gas | $135,772 | 30,626 |
MMBtu
|
$4.43 |
| Coal | $142,572 | 69,305 |
MMBtu
|
$2.06 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $26,582 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $16,659 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Coal Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,967 | - | - |
$3,867
-
MMBtu
|
- | $(-900.0) | |
| 02 | 2.2511: Insulate bare equipment | $5,424 | $2,400 | - |
$2,716
-
MMBtu
|
$2,708
-
MMBtu
|
- | |
| 03 | 2.2135: Repair and eliminate steam leaks | $4,358 | $87 | - |
$2,173
-
MMBtu
|
$2,185
-
MMBtu
|
- | |
| 04 | 2.2136: Install / repair insulation on steam lines | $3,910 | $614 | - |
$1,949
-
MMBtu
|
$1,961
-
MMBtu
|
- | |
| 05 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $7,410 | $12,000 |
$7,410
172,333
kWh
|
- | - | - | |
| 06 | 2.7111: Reduce illumination to minimum necessary levels | $2,513 | - |
$2,513
58,324
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $26,582 | $15,101 |
$9,923
230,657
kWh
|
$10,705
-
MMBtu
|
$6,854
-
MMBtu
|
$(-900.0) | ||
| TOTAL IMPLEMENTED | $16,659 | $3,101 | - |
$10,705
-
MMBtu
|
$6,854
-
MMBtu
|
$(-900.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Coal Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs