ITAC Assessment: TN0267
ITAC logo
ITAC Assessment: TN0267
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1985
Principal Product CANDY
NAICS
n/a
SIC 2064: Candy and Other Confectionery Products
Sales Range $10
M
to 50
M
# of Employees 498
Plant Area
n/a
Annual Production 41,000,000
lb
Production Hrs. Annual 6,120
hrs
Location (State) Tennessee

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $499,073 11,470,106
kWh
Natural Gas $135,772 30,626
MMBtu
Coal $142,572 69,305
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $26,582 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,659

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Coal Savings Administrative Changes Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $2,967 - - $3,867
-
MMBtu
- $(-900.0)
02 2.2511: Insulate bare equipment $5,424 $2,400 - $2,716
-
MMBtu
$2,708
-
MMBtu
-
03 2.2135: Repair and eliminate steam leaks $4,358 $87 - $2,173
-
MMBtu
$2,185
-
MMBtu
-
04 2.2136: Install / repair insulation on steam lines $3,910 $614 - $1,949
-
MMBtu
$1,961
-
MMBtu
-
05 2.2614: Use cooling tower or economizer to replace chiller cooling $7,410 $12,000 $7,410
172,333
kWh
- - -
06 2.7111: Reduce illumination to minimum necessary levels $2,513 - $2,513
58,324
kWh
- - -
TOTAL RECOMMENDED $26,582 $15,101 $9,923
230,657
kWh
$10,705
-
MMBtu
$6,854
-
MMBtu
$(-900.0)
TOTAL IMPLEMENTED $16,659 $3,101 - $10,705
-
MMBtu
$6,854
-
MMBtu
$(-900.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Coal Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs