| Assessment Year | 1985 |
|---|---|
| Principal Product | ASPHALT |
| NAICS |
n/a
|
| SIC | 2951: Asphalt Paving Mixtures and Blocks |
| Sales Range | $1 M to 5M |
| # of Employees | 4 |
| Plant Area |
n/a
|
| Annual Production | 110,000
ton
|
| Production Hrs. Annual | 0
hrs
|
| Location (State) | Tennessee |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $63,659 | 930,832 |
kWh
|
$0.068 |
| Natural Gas | $139,276 | 28,014 |
MMBtu
|
$4.97 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $45,378 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,378 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings |
|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $30,492 | $4,000 |
$30,492
448,417
kWh
|
|
| 02 | 2.2511: Insulate bare equipment | $9,426 | $300 |
$9,426
138,628
kWh
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,460 | $300 |
$5,460
80,305
kWh
|
|
| TOTAL RECOMMENDED | $45,378 | $4,600 |
$45,378
667,350
kWh
|
||
| TOTAL IMPLEMENTED | $45,378 | $4,600 |
$45,378
667,350
kWh
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs