ITAC Assessment: TA0094
ITAC logo
ITAC Assessment: TA0094
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Wheat Flour
NAICS 311211: Flour Milling
SIC 2041: Flour and Other Grain Mill Products
Sales Range $50
M
to 100
M
# of Employees 120
Plant Area 800,000
ft2
Annual Production 781,000,000
lb
Production Hrs. Annual 8,520
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,351,989 28,631,474
kWh
Electricity Demand $261,379 52,910
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,950 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,810

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,225 $410 $5,700
120,760
kWh
$525
-
kW-mo/yr
02 2.4239: Eliminate or reduce compressed air usage $4,585 $125 $4,200
88,980
kWh
$385
-
kW-mo/yr
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,640 - $1,500
31,900
kWh
$140
-
kW-mo/yr
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $325 - $265
5,606
kWh
$60
-
kW-mo/yr
05 2.6218: Turn off equipment when not in use $175 - $175
3,700
kWh
-
TOTAL RECOMMENDED $12,950 $535 $11,840
250,946
kWh
$1,110
-
kW-mo/yr
TOTAL IMPLEMENTED $10,810 $535 $9,900
209,740
kWh
$910
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs