ITAC Assessment: SF0637
ITAC logo
ITAC Assessment: SF0637
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Plastic Packaging
NAICS 326111: Plastics Bag and Pouch Manufacturing
SIC 2656: Sanitary Food Containers, Except Folding
Sales Range $100
M
to 500
M
# of Employees 382
Plant Area 260,000
ft2
Annual Production 147,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,532,523 19,072,000
kWh
Electricity Demand $634,792 33,396
kW-mo/yr
Natural Gas $1,191 523
MMBtu
TOTAL YEARLY COSTS $3,168,506
RECOMMENDED SAVINGS* $645,243 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $33,495 - $35,895
270,288
kWh
- $(-2,400.0)
02 2.6218: Turn off equipment when not in use $71,540 - $71,540
538,708
kWh
- -
03 2.6218: Turn off equipment when not in use $62,779 $13,540 $62,779
472,727
kWh
- -
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $749 $311 $623
4,697
kWh
$126
-
kW-mo/yr
-
05 2.6218: Turn off equipment when not in use $32,229 $20,192 $32,229
242,683
kWh
- -
06 2.6218: Turn off equipment when not in use $2,986 $2,376 $2,986
22,482
kWh
- -
07 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $154,683 $168,414 $129,293
973,564
kWh
$25,390
-
kW-mo/yr
-
08 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $27,397 $47,899 $27,397
206,304
kWh
- -
09 2.9114: Use solar heat to make electricty $259,385 $1,308,722 $259,385
1,953,197
kWh
- -
TOTAL RECOMMENDED $645,243 $1,561,454 $622,127
4,684,650
kWh
$25,516
-
kW-mo/yr
$(-2,400.0)
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs