Assessment Year | 2020 |
---|---|
Principal Product | Beer |
NAICS | 312120: Breweries |
SIC | 2082: Malt Beverages |
Sales Range | $5 M to 10M |
# of Employees | 35 |
Plant Area |
25,700
ft2
|
Annual Production | 3,500,000
units
|
Production Hrs. Annual | 4,914
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $60,551 | 532,522 |
kWh
|
$0.11 | |
Electricity Demand | $50,859 | 1,505 |
kW-mo/yr
|
$33.79 | |
Natural Gas | $16,032 | 1,349 |
MMBtu
|
$11.88 | |
Waste Disposal Costs | |||||
Water Usage | $24,446 | 1,204,253 |
Tgal
|
$0.020 | |
TOTAL YEARLY COSTS | $151,888 | ||||
RECOMMENDED SAVINGS* | $24,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $24,309 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,782 | $1,359 |
$4,782
42,054
kWh
|
- | - | - | - | |
02 | 2.2511: Insulate bare equipment | $1,259 | $787 | - | - |
$1,259
-
MMBtu
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $3,899 | $4,002 |
$3,899
34,289
kWh
|
- | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $11,809 | $17,557 |
$5,924
52,096
kWh
|
$5,320
-
kW-mo/yr
|
- | $601 | $(-36.0) | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,560 | $12,365 |
$2,560
22,507
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $24,309 | $36,070 |
$17,165
150,946
kWh
|
$5,320
-
kW-mo/yr
|
$1,259
-
MMBtu
|
$601 | $(-36.0) | ||
TOTAL IMPLEMENTED | $24,309 | $36,070 |
$17,165
150,946
kWh
|
$5,320
-
kW-mo/yr
|
$1,259
-
MMBtu
|
$601 | $(-36.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs