| Assessment Year | 2017 |
|---|---|
| Principal Product | Machine Components |
| NAICS | 333999: All Other Miscellaneous General Purpose Machinery Manufacturing |
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 105 |
| Plant Area |
65,000
ft2
|
| Annual Production | 500,000
units
|
| Production Hrs. Annual | 8,076
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $199,733 | 1,920,177 |
kWh
|
$0.10 |
| Electricity Demand | $104,648 | 3,636 |
kW-mo/yr
|
$28.78 |
| Natural Gas | $2,463 | 254 |
MMBtu
|
$9.69 |
| TOTAL YEARLY COSTS | $306,843 | |||
| RECOMMENDED SAVINGS* | $120,727 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $120,127 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $9,800 | - |
$9,800
94,211
kWh
|
- | - | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,955 | - |
$7,155
68,782
kWh
|
- | - | $(-1,200.0) | - | |
| 03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $600 | - | - | - | $600 | - | - | |
| 04 | 2.4323: Use optimum size and capacity equipment | $18,778 | $30,000 |
$13,617
130,909
kWh
|
$5,161
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $8,191 | $12,954 |
$3,979
38,256
kWh
|
$4,014
-
kW-mo/yr
|
- | $495 | $(-297.0) | |
| 06 | 2.9114: Use solar heat to make electricty | $77,403 | $434,700 |
$43,759
420,682
kWh
|
$33,644
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $120,727 | $477,654 |
$78,310
752,840
kWh
|
$42,819
-
kW-mo/yr
|
$600 | $(-705.0) | $(-297.0) | ||
| TOTAL IMPLEMENTED | $120,127 | $477,654 |
$78,310
752,840
kWh
|
$42,819
-
kW-mo/yr
|
- | $(-705.0) | $(-297.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs