ITAC Assessment: SF0492
ITAC logo
ITAC Assessment: SF0492
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product condensed and powdered milk
NAICS 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing
SIC 2023: Dry, Condensed, and Evaporated Dairy Products
Sales Range $50
M
to 100
M
# of Employees 42
Plant Area 90,000
ft2
Annual Production 400,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $729,533 8,279,616
kWh
Electricity Demand $212,666 18,847
kW-mo/yr
Natural Gas $486,281 92,009
MMBtu
TOTAL YEARLY COSTS $1,428,480
RECOMMENDED SAVINGS* $117,514 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $100,369

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.2121: Increase amount of condensate returned $13,265 $280 - - $13,265
-
MMBtu
- -
02 2.4111: Utilize energy-efficient belts and other improved mechanisms $218 $33 $165
1,874
kWh
$53
-
kW-mo/yr
- - -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $18,076 $5,200 $15,379
174,541
kWh
$2,697
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $15,543 $7,437 $14,379
163,197
kWh
$1,952
-
kW-mo/yr
- $414 $(-1,202.0)
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $8,830 $14,614 $8,830
100,220
kWh
- - - -
06 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $8,794 $15,281 $7,460
84,663
kWh
$1,334
-
kW-mo/yr
- - -
07 2.1243: Use heat from boiler blowdown to preheat boiler feed water $6,867 $11,727 - - $6,867
-
MMBtu
- -
08 2.2511: Insulate bare equipment $7,565 $13,378 - - $7,565
-
MMBtu
- -
09 2.2511: Insulate bare equipment $165 $292 - - $165
-
MMBtu
- -
10 2.7135: Install occupancy sensors $8,681 $17,643 $7,386
83,828
kWh
$1,295
-
kW-mo/yr
- - -
11 2.2121: Increase amount of condensate returned $12,365 $30,659 - - $12,365
-
MMBtu
- -
12 2.2437: Recover waste heat from equipment $17,145 $45,338 - - $17,145
-
MMBtu
- -
TOTAL RECOMMENDED $117,514 $161,882 $53,599
608,323
kWh
$7,331
-
kW-mo/yr
$57,372
-
MMBtu
$414 $(-1,202.0)
TOTAL IMPLEMENTED $100,369 $116,544 $53,599
608,323
kWh
$7,331
-
kW-mo/yr
$40,227
-
MMBtu
$414 $(-1,202.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs