Assessment Year | 2016 |
---|---|
Principal Product | condensed and powdered milk |
NAICS | 311514: Dry, Condensed, and Evaporated Dairy Product Manufacturing |
SIC | 2023: Dry, Condensed, and Evaporated Dairy Products |
Sales Range | $50 M to 100M |
# of Employees | 42 |
Plant Area |
90,000
ft2
|
Annual Production | 400,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $729,533 | 8,279,616 |
kWh
|
$0.088 |
Electricity Demand | $212,666 | 18,847 |
kW-mo/yr
|
$11.28 |
Natural Gas | $486,281 | 92,009 |
MMBtu
|
$5.29 |
TOTAL YEARLY COSTS | $1,428,480 | |||
RECOMMENDED SAVINGS* | $117,514 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $100,369 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2121: Increase amount of condensate returned | $13,265 | $280 | - | - |
$13,265
-
MMBtu
|
- | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $218 | $33 |
$165
1,874
kWh
|
$53
-
kW-mo/yr
|
- | - | - | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $18,076 | $5,200 |
$15,379
174,541
kWh
|
$2,697
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $15,543 | $7,437 |
$14,379
163,197
kWh
|
$1,952
-
kW-mo/yr
|
- | $414 | $(-1,202.0) | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $8,830 | $14,614 |
$8,830
100,220
kWh
|
- | - | - | - | |
06 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $8,794 | $15,281 |
$7,460
84,663
kWh
|
$1,334
-
kW-mo/yr
|
- | - | - | |
07 | 2.1243: Use heat from boiler blowdown to preheat boiler feed water | $6,867 | $11,727 | - | - |
$6,867
-
MMBtu
|
- | - | |
08 | 2.2511: Insulate bare equipment | $7,565 | $13,378 | - | - |
$7,565
-
MMBtu
|
- | - | |
09 | 2.2511: Insulate bare equipment | $165 | $292 | - | - |
$165
-
MMBtu
|
- | - | |
10 | 2.7135: Install occupancy sensors | $8,681 | $17,643 |
$7,386
83,828
kWh
|
$1,295
-
kW-mo/yr
|
- | - | - | |
11 | 2.2121: Increase amount of condensate returned | $12,365 | $30,659 | - | - |
$12,365
-
MMBtu
|
- | - | |
12 | 2.2437: Recover waste heat from equipment | $17,145 | $45,338 | - | - |
$17,145
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $117,514 | $161,882 |
$53,599
608,323
kWh
|
$7,331
-
kW-mo/yr
|
$57,372
-
MMBtu
|
$414 | $(-1,202.0) | ||
TOTAL IMPLEMENTED | $100,369 | $116,544 |
$53,599
608,323
kWh
|
$7,331
-
kW-mo/yr
|
$40,227
-
MMBtu
|
$414 | $(-1,202.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs