Assessment Year | 2000 |
---|---|
Principal Product | Ready Mix Concrete |
NAICS |
n/a
|
SIC | 3273: Ready-Mixed Concrete |
Sales Range | $5 M to 10M |
# of Employees | 20 |
Plant Area |
103,000
ft2
|
Annual Production | 11,968
ton
|
Production Hrs. Annual | 3,097
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,563 | 646,542 |
kWh
|
$0.083 |
Electricity Demand | $13,607 | 3,271 |
kW-mo/yr
|
$4.16 |
Natural Gas | $1,869 | 250 |
MMBtu
|
$7.48 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,015 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,763 | $1,915 |
$1,501
18,464
kWh
|
$262
-
kW-mo/yr
|
|
02 | 2.4133: Use most efficient type of electric motors | $252 | $654 |
$210
2,638
kWh
|
$42
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $2,015 | $2,569 |
$1,711
21,102
kWh
|
$304
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs