Assessment Year | 1999 |
---|---|
Principal Product | Peppers, Olives, and Specialties |
NAICS |
n/a
|
SIC | 2014: |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
80,000
ft2
|
Annual Production | 2,000,000
units
|
Production Hrs. Annual | 3,168
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,324 | 863,130 |
kWh
|
$0.081 |
Electricity Demand | $11,100 | 2,592 |
kW-mo/yr
|
$4.28 |
Natural Gas | $72,896 | 15,357 |
MMBtu
|
$4.75 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $45,299 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,303 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.1231: Establish burner maintenance schedule for boilers | $1,431 | - | - | - |
$1,431
-
MMBtu
|
- | - | - | |
02 | 2.2136: Install / repair insulation on steam lines | $850 | $788 | - | - |
$850
-
MMBtu
|
- | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $442 | $600 |
$375
4,689
kWh
|
$67
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7144: Install spectral reflectors / delamp | $6,772 | $16,500 |
$6,016
73,857
kWh
|
$756
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7134: Use photocell controls | $3,556 | $14,000 |
$3,158
38,687
kWh
|
$398
-
kW-mo/yr
|
- | - | - | - | |
06 | 3.5316: Contract a wood pallet recycling company | $240 | $200 | - | - | - | - |
$240
-
lb
|
- | |
07 | 3.5313: Increase amount of waste recovered for resale | $10,000 | $200 | - | - | - | - |
$10,000
-
lb
|
- | |
08 | 3.4114: Replace city water with recycled water via cooling tower | $7,184 | $3,721 | - | - | - |
$7,184
-
Tgal
|
- | - | |
09 | 3.4113: Treat and reuse rinse waters | $3,340 | $3,269 | - | - | - |
$3,340
-
Tgal
|
- | - | |
10 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $11,484 | $15,374 |
$(-30.0)
(-293)
kWh
|
- | - | - |
$12,014
-
lb
|
$(-500.0) | |
TOTAL RECOMMENDED | $45,299 | $54,652 |
$9,519
116,940
kWh
|
$1,221
-
kW-mo/yr
|
$2,281
-
MMBtu
|
$10,524
-
Tgal
|
$22,254
-
lb
|
$(-500.0) | ||
TOTAL IMPLEMENTED | $16,303 | $5,057 |
$375
4,689
kWh
|
$67
-
kW-mo/yr
|
$2,281
-
MMBtu
|
$3,340
-
Tgal
|
$10,240
-
lb
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs