ITAC Assessment: SD0671
ITAC logo
ITAC Assessment: SD0671
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Packaging
NAICS 423910: Sporting and Recreational Goods and Supplies Merchant Wholesalers
SIC 4225: General Warehousing and Storage
Sales Range greater than $500
M
# of Employees 65
Plant Area 289,407
ft2
Annual Production 277,862
units
Production Hrs. Annual 3,125
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,457 327,932
kWh
Electricity Demand $24,334 1,416
kW-mo/yr
Electricity Fees $2,741 -
LPG $15,691 178
MMBtu
TOTAL YEARLY COSTS $125,223
RECOMMENDED SAVINGS* $101,682 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings LPG Savings
01 2.9114: Use solar heat to make electricty $72,797 $103,994 $56,716
225,602
kWh
$16,080
-
kW-mo/yr
-
02 2.3141: Use battery storage for demand control $2,541 $1,352 $(-2,551.0)
(-10,147)
kWh
$5,092
-
kW-mo/yr
-
03 2.3132: Recharge batteries on during off-peak demand periods $3,996 - - $3,996
-
kW-mo/yr
-
04 2.1321: Replace fossil fuel equipment with electrical equipment $14,911 $23,188 $(-780.0)
(-3,103)
kWh
- $15,691
-
MMBtu
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,033 $9,226 $5,333
21,214
kWh
$700
-
kW-mo/yr
-
06 2.7224: Reduce space conditioning during non-working hours $1,404 - $1,298
5,163
kWh
$107
-
kW-mo/yr
-
TOTAL RECOMMENDED $101,682 $137,760 $60,017
238,730
kWh
$25,974
-
kW-mo/yr
$15,691
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings LPG Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs