| Assessment Year | 2009 |
|---|---|
| Principal Product | AIRCRAFT FASTENERS |
| NAICS | 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing |
| SIC | 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified |
| Sales Range | less than $500 k |
| # of Employees | 160 |
| Plant Area |
75,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 6,426
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $249,130 | 3,075,657 |
kWh
|
$0.081 |
| Electricity Demand | $159,339 | 8,522 |
kW-mo/yr
|
$18.70 |
| Electricity Fees | $12,647 | - |
|
- |
| Natural Gas | $25,627 | 2,801 |
MMBtu
|
$9.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $49,124 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $46,359 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $31,588 | - | - |
$31,588
-
kW-mo/yr
|
|
| 02 | 2.3132: Recharge batteries on during off-peak demand periods | $5,480 | - | - |
$5,480
-
kW-mo/yr
|
|
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,840 | $2,200 |
$6,840
84,460
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,765 | $2,554 |
$1,903
23,499
kWh
|
$862
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,451 | $4,146 |
$2,451
30,264
kWh
|
- | |
| TOTAL RECOMMENDED | $49,124 | $8,900 |
$11,194
138,223
kWh
|
$37,930
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $46,359 | $6,346 |
$9,291
114,724
kWh
|
$37,068
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs