Assessment Year | 2009 |
---|---|
Principal Product | treated water |
NAICS | 221310: Water Supply and Irrigation Systems |
SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
Sales Range | less than $500 k |
# of Employees | 18 |
Plant Area |
1,000,000
ft2
|
Annual Production | 9,125
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $642,075 | 7,419,616 |
kWh
|
$0.087 |
Electricity Demand | $187,039 | 13,552 |
kW-mo/yr
|
$13.80 |
Electricity Fees | $53,576 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $106,509 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,063 | $19,400 |
$19,063
220,387
kWh
|
- | |
02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,436 | $26,587 |
$29,436
340,308
kWh
|
- | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,630 | $4,249 |
$1,630
10,070
kWh
|
- | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,003 | $16,190 |
$7,982
92,275
kWh
|
$1,021
-
kW-mo/yr
|
|
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,392 | $14,325 |
$3,392
38,059
kWh
|
- | |
06 | 2.4131: Size electric motors for peak operating efficiency | $43,985 | $8,096 |
$38,134
440,859
kWh
|
$5,851
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $106,509 | $88,847 |
$99,637
1,141,958
kWh
|
$6,872
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs