| Assessment Year | 2009 |
|---|---|
| Principal Product | treated water |
| NAICS | 221310: Water Supply and Irrigation Systems |
| SIC | 3589: Service Industry Machinery, Not Elsewhere Classified |
| Sales Range | less than $500 k |
| # of Employees | 18 |
| Plant Area |
1,000,000
ft2
|
| Annual Production | 9,125
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $642,075 | 7,419,616 |
kWh
|
$0.087 |
| Electricity Demand | $187,039 | 13,552 |
kW-mo/yr
|
$13.80 |
| Electricity Fees | $53,576 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $106,509 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $19,063 | $19,400 |
$19,063
220,387
kWh
|
- | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $29,436 | $26,587 |
$29,436
340,308
kWh
|
- | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,630 | $4,249 |
$1,630
10,070
kWh
|
- | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $9,003 | $16,190 |
$7,982
92,275
kWh
|
$1,021
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,392 | $14,325 |
$3,392
38,059
kWh
|
- | |
| 06 | 2.4131: Size electric motors for peak operating efficiency | $43,985 | $8,096 |
$38,134
440,859
kWh
|
$5,851
-
kW-mo/yr
|
|
| TOTAL RECOMMENDED | $106,509 | $88,847 |
$99,637
1,141,958
kWh
|
$6,872
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs