| Assessment Year | 2008 |
|---|---|
| Principal Product | Slit and Cut Coil Steel |
| NAICS | 331210: Iron and Steel Pipe and Tube Manufacturing from Purchased Steel |
| SIC | 5051: Metals Service Centers and Offices |
| Sales Range | $50 M to 100M |
| # of Employees | 54 |
| Plant Area |
100,000
ft2
|
| Annual Production | 40,000
ton
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $65,738 | 810,940 |
kWh
|
$0.081 |
| Electricity Demand | $42,610 | 3,407 |
kW-mo/yr
|
$12.51 |
| Electricity Fees | $696 | - |
|
- |
| Natural Gas | $331 | 261 |
MMBtu
|
$1.27 |
| Other Gas | $165 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $21,709 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,081 | $28,585 |
$10,089
124,401
kWh
|
$2,992
-
kW-mo/yr
|
|
| 02 | 2.7134: Use photocell controls | $5,157 | $4,950 |
$5,157
63,589
kWh
|
- | |
| 03 | 2.4133: Use most efficient type of electric motors | $1,238 | $2,428 |
$750
9,251
kWh
|
$488
-
kW-mo/yr
|
|
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,111 | $6,578 |
$773
9,530
kWh
|
$338
-
kW-mo/yr
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,030 | $3,394 |
$1,030
12,696
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $92 | $200 |
$92
1,133
kWh
|
- | |
| TOTAL RECOMMENDED | $21,709 | $46,135 |
$17,891
220,600
kWh
|
$3,818
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs