| Assessment Year | 2006 |
|---|---|
| Principal Product | Pharmaceuticals |
| NAICS | 541712: Research and Development in the Physical, Engineering, and Life Sciences (except Biotechnology) |
| SIC | 8731: Commercial Physical and Biological Research |
| Sales Range | less than $500 k |
| # of Employees | 450 |
| Plant Area |
350,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | California |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $970,069 | 10,544,904 |
kWh
|
$0.092 |
| Electricity Demand | $323,985 | 21,200 |
kW-mo/yr
|
$15.28 |
| Natural Gas | $389,302 | 46,236 |
MMBtu
|
$8.42 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $231,093 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,234 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $170,338 | $792,300 |
$129,527
1,407,900
kWh
|
$104,515
-
kW-mo/yr
|
$(-45,754.0)
-
MMBtu
|
$(-17,950.0) | |
| 02 | 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary | $27,521 | - |
$22,402
243,494
kWh
|
$5,119
-
kW-mo/yr
|
- | - | |
| 03 | 2.7226: Use computer programs to optimize hvac performance | $16,633 | - |
$16,633
180,796
kWh
|
- | - | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $10,124 | $15,000 | - | - |
$10,124
-
MMBtu
|
- | |
| 05 | 2.2163: Use minimum steam operating pressure | $1,208 | - | - | - |
$1,208
-
MMBtu
|
- | |
| 06 | 2.7135: Install occupancy sensors | $2,957 | $384 |
$2,957
32,140
kWh
|
- | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,312 | $6,160 |
$1,533
16,661
kWh
|
$779
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $231,093 | $813,844 |
$173,052
1,880,991
kWh
|
$110,413
-
kW-mo/yr
|
$(-34,422.0)
-
MMBtu
|
$(-17,950.0) | ||
| TOTAL IMPLEMENTED | $33,234 | $21,544 |
$21,123
229,597
kWh
|
$779
-
kW-mo/yr
|
$11,332
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs