Assessment Year | 2001 |
---|---|
Principal Product | metal parts for automobile industry |
NAICS |
n/a
|
SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 102 |
Plant Area |
80,000
ft2
|
Annual Production | 900
ton
|
Production Hrs. Annual | 7,200
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $238,023 | 4,625,850 |
kWh
|
$0.051 |
Electricity Demand | $92,639 | 9,058 |
kW-mo/yr
|
$10.23 |
Electricity Fees | $3,588 | - |
|
- |
Natural Gas | $31,720 | 5,525 |
MMBtu
|
$5.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $121,362 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $80,384 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.2425: Use flue gases to heat process or service water | $4,061 | $10,250 | - |
$4,061
-
MMBtu
|
- | - | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $4,459 | $4,000 | - |
$4,459
-
MMBtu
|
- | - | - | - | |
03 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $17,320 | - |
$12,600
-
kW-mo/yr
|
- | - | - | - | $4,720 | |
04 | 2.3134: Shift from daytime to nighttime operation | $2,492 | - |
$1,728
-
kW-mo/yr
|
- | - | - | - | $764 | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,500 | $7,900 | - | - | - | - | $4,500 | - | |
06 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,850 | $2,100 | - | - | - | - | $4,850 | - | |
07 | 3.8121: Cover containers to minimize evaporative losses | $8,708 | $15,000 | - | - |
$8,708
-
gal
|
- | - | - | |
08 | 2.8114: Change rate schedules or other changes in utility service | $59,514 | - | - | - | - | - | - | $59,514 | |
09 | 4.445: Install equipment to move product | $14,400 | $25,000 | - | - | - | $14,400 | - | - | |
10 | 4.821: Pay bills on time to avoid late fees | $1,058 | - | - | - | - | - | $1,058 | - | |
TOTAL RECOMMENDED | $121,362 | $64,250 |
$14,328
-
kW-mo/yr
|
$8,520
-
MMBtu
|
$8,708
-
gal
|
$14,400 | $10,408 | $64,998 | ||
TOTAL IMPLEMENTED | $80,384 | - |
$14,328
-
kW-mo/yr
|
- | - | - | $1,058 | $64,998 | ||
Yearly Savings* | Imp'd Cost* | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs