| Assessment Year | 2025 |
|---|---|
| Principal Product | Research |
| NAICS | 423690: Other Electronic Parts and Equipment Merchant Wholesalers |
| SIC | 5065: Electronic Parts and Equipment, Not Elsewhere Classified |
| Sales Range | less than $500 k |
| # of Employees | 325 |
| Plant Area |
200,000
ft2
|
| Annual Production | 1,000
units
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $628,591 | 9,823,622 |
kWh
|
$0.064 |
| Electricity Demand | $295,864 | 33,169 |
kW-mo/yr
|
$8.92 |
| Electricity Fees | $46,336 | - |
|
- |
| Natural Gas | $110,874 | 14,191 |
MMBtu
|
$7.81 |
| TOTAL YEARLY COSTS | $1,081,665 | |||
| RECOMMENDED SAVINGS* | $35,543 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7314: Reduce ventilation air | $13,430 | - |
$13,430
209,879
kWh
|
- | - | |
| 02 | 2.2614: Use cooling tower or economizer to replace chiller cooling | $8,055 | - |
$8,055
125,874
kWh
|
- | - | |
| 03 | 2.7314: Reduce ventilation air | $6,836 | - |
$771
12,052
kWh
|
- |
$6,065
-
MMBtu
|
|
| 04 | 2.7111: Reduce illumination to minimum necessary levels | $3,076 | - |
$3,076
48,075
kWh
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,146 | $30,877 |
$2,176
34,002
kWh
|
$1,970
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $35,543 | $30,877 |
$27,508
429,882
kWh
|
$1,970
-
kW-mo/yr
|
$6,065
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs