| Assessment Year | 2019 |
|---|---|
| Principal Product | Packed Apples |
| NAICS | 111331: Apple Orchards |
| SIC | 0175: Deciduous Tree Fruits |
| Sales Range | $10 M to 50M |
| # of Employees | 115 |
| Plant Area |
183,000
ft2
|
| Annual Production | 1,000,000
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Washington |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $185,461 | 10,860,340 |
kWh
|
$0.017 |
| TOTAL YEARLY COSTS | $185,461 | |||
| RECOMMENDED SAVINGS* | $68,101 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $35,763 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.3128: Utilize other methods to remove contaminants | $27,061 | $33,855 |
$(-1,615.0)
(-65,323)
kWh
|
- | - | $29,000 | $(-324.0) | |
| 02 | 2.3212: Optimize plant power factor | $31,433 | $68,000 | - | - | $31,433 | - | - | |
| 03 | 2.2621: Modify refrigeration system to operate at a lower pressure | $4,330 | $1,100 |
$3,947
159,649
kWh
|
$383
-
kW-mo/yr
|
- | - | - | |
| 04 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $3,139 | $2,013 |
$2,539
102,796
kWh
|
$600
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $2,138 | $3,275 |
$1,949
78,849
kWh
|
$189
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $68,101 | $108,243 |
$6,820
275,971
kWh
|
$1,172
-
kW-mo/yr
|
$31,433 | $29,000 | $(-324.0) | ||
| TOTAL IMPLEMENTED | $35,763 | $69,100 |
$3,947
159,649
kWh
|
$383
-
kW-mo/yr
|
$31,433 | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs