Assessment Year | 2018 |
---|---|
Principal Product | Water |
NAICS | 221330: Steam and Air-Conditioning Supply |
SIC | 4961: Steam and Air-Conditioning Supply |
Sales Range | $1 M to 5M |
# of Employees | 36 |
Plant Area |
7,000
ft2
|
Annual Production | 12,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $2,156,311 | 37,830,013 |
kWh
|
$0.057 | |
Electricity Demand | $158,608 | 61,003 |
kW-mo/yr
|
$2.60 | |
Electricity Fees | $(-1,869,325.0) | - |
|
- | |
Natural Gas | $786,893 | 378,894 |
MMBtu
|
$2.08 | |
Waste Disposal Costs | |||||
Water Usage | $264,588 | 37,801 |
Tgal
|
$7.00 | |
TOTAL YEARLY COSTS | $1,497,075 | ||||
RECOMMENDED SAVINGS* | $56,345 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $33,259 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $23,086 | $32,488 |
$21,780
382,114
kWh
|
$1,306
-
kW-mo/yr
|
- | - | - | |
02 | 2.2414: Use waste heat from hot flue gases to preheat | $14,884 | $53,702 | - | - |
$14,884
-
MMBtu
|
- | - | |
03 | 2.2511: Insulate bare equipment | $7,954 | $8,965 | - | - |
$7,954
-
MMBtu
|
- | - | |
04 | 2.5123: Reduce fluid flow rates | $6,509 | $7,384 |
$6,008
105,412
kWh
|
$501
-
kW-mo/yr
|
- | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,481 | $19,583 |
$1,782
31,269
kWh
|
$111
-
kW-mo/yr
|
- | $739 | $(-151.0) | |
06 | 2.1116: Improve combustion control capability | $1,431 | $5,365 |
$1,301
22,829
kWh
|
$130
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $56,345 | $127,487 |
$30,871
541,624
kWh
|
$2,048
-
kW-mo/yr
|
$22,838
-
MMBtu
|
$739 | $(-151.0) | ||
TOTAL IMPLEMENTED | $33,259 | $94,999 |
$9,091
159,510
kWh
|
$742
-
kW-mo/yr
|
$22,838
-
MMBtu
|
$739 | $(-151.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs