ITAC Assessment: OR0675
ITAC logo
ITAC Assessment: OR0675
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2016
Principal Product Liquid Packaging
NAICS 322219: Other Paperboard Container Manufacturing
SIC 2655: Fiber Cans, Tubes, Drums, and Similar Products
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 138,519
ft2
Annual Production 120,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $301,631 6,496,460
kWh
Electricity Demand $117,817 16,409
kW-mo/yr
Electricity Fees $12,655 -
Natural Gas $90,576 15,541
MMBtu
TOTAL YEARLY COSTS $522,678
RECOMMENDED SAVINGS* $136,193 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $132,994

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 4.445: Install equipment to move product $79,123 $89,654 $3,403
73,291
kWh
- $75,720
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,062 $1,969 $31,062
668,999
kWh
- -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $22,809 $23,810 $19,468
419,308
kWh
$3,341
-
kW-mo/yr
-
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $3,199 $7,215 $3,199
68,902
kWh
- -
TOTAL RECOMMENDED $136,193 $122,648 $57,132
1,230,500
kWh
$3,341
-
kW-mo/yr
$75,720
TOTAL IMPLEMENTED $132,994 $115,433 $53,933
1,161,598
kWh
$3,341
-
kW-mo/yr
$75,720
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs