ITAC Assessment: OR0618
ITAC logo
ITAC Assessment: OR0618
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2013
Principal Product Breakfast Cereal
NAICS 311230: Breakfast Cereal Manufacturing
SIC 2043: Cereal Breakfast Foods
Sales Range $5
M
to 10
M
# of Employees 200
Plant Area 122,000
ft2
Annual Production 875,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,459 4,467,896
kWh
Electricity Demand $87,474 13,775
kW-mo/yr
Electricity Fees $9,798 -
Natural Gas $220,784 40,266
MMBtu
LPG $26,637 1,037
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,221 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,881 $3,300 $1,993
35,412
kWh
$888
-
kW-mo/yr
- - -
02 4.454: Modify startup/shutdown times $10,380 $800 $10,380
184,405
kWh
- - - -
03 2.7135: Install occupancy sensors $977 $1,975 $808
12,784
kWh
- - $87 $82
04 3.7212: Improved material handling (mixing and transfer) $9,796 $50,179 $(-605.0)
(-10,742)
kWh
$(-767.0)
-
kW-mo/yr
$12,168 $(-1,000.0) -
05 2.7243: Improve air circulation with destratification fans / other methods $4,187 $2,283 $3,427
60,882
kWh
$760
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $28,221 $58,537 $16,003
282,741
kWh
$881
-
kW-mo/yr
$12,168 $(-913.0) $82
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs