Assessment Year | 2010 |
---|---|
Principal Product | Wood Boards, Chip |
NAICS | 321113: Sawmills |
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 133 |
Plant Area |
565,000
ft2
|
Annual Production | 1,150,000
units
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $675,263 | 16,628,000 |
kWh
|
$0.041 |
Electricity Demand | $200,860 | 60,912 |
kW-mo/yr
|
$3.30 |
Electricity Fees | $142,019 | - |
|
- |
Wood | $597,904 | 434,237 |
MMBtu
|
$1.38 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,401,516 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $265,603 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $35,913 | $17,860 |
$35,913
862,672
kWh
|
- | - | |
02 | 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat | $219,003 | $250,000 |
$850,000
13,808,232
kWh
|
$(-390,000.0)
-
MMBtu
|
$(-240,997.0) | |
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $46,600 | $244,000 |
$46,600
1,120,000
kWh
|
- | - | |
04 | 3.1191: Change procedures / equipment / operating conditions | $1,100,000 | $2,150,000 | - | - | $1,100,000 | |
TOTAL RECOMMENDED | $1,401,516 | $2,661,860 |
$932,513
15,790,904
kWh
|
$(-390,000.0)
-
MMBtu
|
$859,003 | ||
TOTAL IMPLEMENTED | $265,603 | $494,000 |
$896,600
14,928,232
kWh
|
$(-390,000.0)
-
MMBtu
|
$(-240,997.0) |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs