| Assessment Year | 2009 |
|---|---|
| Principal Product | Treated wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | $10 M to 50M |
| # of Employees | 26 |
| Plant Area |
1,306,800
ft2
|
| Annual Production | 5,694,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Oregon |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $180,500 | 4,724,280 |
kWh
|
$0.038 |
| Electricity Demand | $36,401 | 9,630 |
kW-mo/yr
|
$3.78 |
| Electricity Fees | $37,784 | - |
|
- |
| Natural Gas | $24 | 1,863 |
MMBtu
|
$0.013 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,059 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $56,059 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4322: Use or replace with energy efficient substitutes | $30,000 | $81,700 |
$27,000
565,400
kWh
|
$3,000
-
kW-mo/yr
|
- | - | |
| 02 | 2.4322: Use or replace with energy efficient substitutes | $15,352 | $35,800 |
$13,812
289,080
kWh
|
$1,540
-
kW-mo/yr
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $8,055 | $6,600 |
$5,515
115,457
kWh
|
$185
-
kW-mo/yr
|
$721 | $1,634 | |
| 04 | 2.4133: Use most efficient type of electric motors | $2,652 | $4,300 |
$2,381
49,835
kWh
|
$271
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $56,059 | $128,400 |
$48,708
1,019,772
kWh
|
$4,996
-
kW-mo/yr
|
$721 | $1,634 | ||
| TOTAL IMPLEMENTED | $56,059 | $128,400 |
$48,708
1,019,772
kWh
|
$4,996
-
kW-mo/yr
|
$721 | $1,634 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs