Assessment Year | 2002 |
---|---|
Principal Product | Precision Machine Parts |
NAICS |
n/a
|
SIC | 3451: Screw Machine Products |
Sales Range | $10 M to 50M |
# of Employees | 110 |
Plant Area |
47,000
ft2
|
Annual Production | 40,000,000
pieces
|
Production Hrs. Annual | 4,200
hrs
|
Location (State) | Oregon |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $109,607 | 1,862,800 |
kWh
|
$0.059 |
Electricity Demand | $30,352 | 6,240 |
kW-mo/yr
|
$4.86 |
Electricity Fees | $1,339 | - |
|
- |
Natural Gas | $15,190 | 1,618 |
MMBtu
|
$9.39 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $26,930 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,897 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,115 | $33,646 |
$9,869
167,736
kWh
|
$2,306
-
kW-mo/yr
|
$(-452.0) | $2,392 | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $2,918 | $3,031 |
$2,081
35,359
kWh
|
$486
-
kW-mo/yr
|
$(-34.0) | $385 | |
03 | 2.4133: Use most efficient type of electric motors | $4,676 | $560 |
$3,775
64,152
kWh
|
$901
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,472 | $3,500 |
$2,547
43,293
kWh
|
$925
-
kW-mo/yr
|
- | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,749 | - |
$1,239
21,051
kWh
|
$510
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $26,930 | $40,737 |
$19,511
331,591
kWh
|
$5,128
-
kW-mo/yr
|
$(-486.0) | $2,777 | ||
TOTAL IMPLEMENTED | $9,897 | $4,060 |
$7,561
128,496
kWh
|
$2,336
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs