ITAC Assessment: OR0312
ITAC logo
ITAC Assessment: OR0312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Paper sheets and rolls
NAICS
n/a
SIC 2678: Stationery, Tablets, and Related Products
Sales Range $10
M
to 50
M
# of Employees 106
Plant Area 85,000
ft2
Annual Production 20,000,000
lb
Production Hrs. Annual 6,120
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,765 1,127,198
kWh
Electricity Demand $13,794 6,816
kW-mo/yr
Electricity Fees $3,612 -
Natural Gas $14,321 3,065
MMBtu
LPG $16,259 1,585
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $145,612 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $78,399

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 4.452: Eliminate shift $25,580 $50,000 - - - - - $3,140
-
lb
$22,440 -
02 3.6193: Install equipment (eg compactor) to reduce disposal costs $4,110 - - - - - - $4,110
-
lb
- -
03 4.652: Replace existing equipment with more suitable substitutes $16,830 $4,300 - - - - - - $16,830 -
04 4.441: Install automatic packing equipment $26,975 $14,685 $(-5.0)
(-293)
kWh
- - - - - $26,980 -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $1,805 $2,100 - $(-30.0)
-
kW-mo/yr
- - - $1,890
-
lb
$(-55.0) -
06 4.423: Move product using mechanical means $46,000 $147,500 - - - - - - - $46,000
07 4.621: Use fixtures to reduce machine changeout times $11,220 $44,000 - - - - - - $11,220 -
08 2.1332: Convert combustion equipment to burn natural gas $8,025 $55,400 $(-460.0)
(-20,223)
kWh
$(-370.0)
-
kW-mo/yr
- $(-7,415.0)
-
MMBtu
$16,270
-
MMBtu
- - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,254 $1,000 $1,254
55,686
kWh
- - - - - - -
10 2.3212: Optimize plant power factor $2,358 $7,000 - - $2,358 - - - - -
11 2.4133: Use most efficient type of electric motors $1,455 $4,459 $678
30,188
kWh
$777
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $145,612 $330,444 $1,467
65,358
kWh
$377
-
kW-mo/yr
$2,358 $(-7,415.0)
-
MMBtu
$16,270
-
MMBtu
$9,140
-
lb
$77,415 $46,000
TOTAL IMPLEMENTED $78,399 $202,959 $1,932
85,874
kWh
$777
-
kW-mo/yr
- - - $7,250
-
lb
$22,440 $46,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings LPG Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs