ITAC Assessment: OR0295
ITAC logo
ITAC Assessment: OR0295
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Pipe Fittings
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 60
Plant Area 53,136
ft2
Annual Production 1,549,913
lb
Production Hrs. Annual 2,000
hrs
Location (State) Oregon

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,767 1,385,111
kWh
Electricity Demand $26,698 75,084
kW-mo/yr
Electricity Fees $492 -
Natural Gas $11,183 2,227
MMBtu
Other Gas $3,673 333
MMBtu
Other Energy $19,971 3,471
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $137,891 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,891

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 4.111: Add equipment/ operators to reduce production bottleneck $86,250 $1,000 - - - - - - - - $86,250
02 4.513: Re-arrange equipment layout to reduce labor costs $36,000 $40,000 - - - - - - $36,000 - -
03 2.2121: Increase amount of condensate returned $1,830 $890 - - - $1,400
-
MMBtu
- $430
-
Tgal
- - -
04 2.1233: Analyze flue gas for proper air/fuel ratio $940 $500 - - - - $940
-
MMBtu
- - - -
05 2.1331: Burn a less expensive grade of fuel $7,820 $10,000 - - $(-11,210.0)
-
MMBtu
- $19,030
-
MMBtu
- - - -
06 2.2514: Cover open tanks $1,160 $1,360 - - $1,160
-
MMBtu
- - - - - -
07 2.7142: Utilize higher efficiency lamps and/or ballasts $3,116 $6,360 $964
33,998
kWh
$802
-
kW-mo/yr
- - - - $989 $361 -
08 2.4133: Use most efficient type of electric motors $775 $2,723 $561
19,930
kWh
$214
-
kW-mo/yr
- - - - - - -
TOTAL RECOMMENDED $137,891 $62,833 $1,525
53,928
kWh
$1,016
-
kW-mo/yr
$(-10,050.0)
-
MMBtu
$1,400
-
MMBtu
$19,970
-
MMBtu
$430
-
Tgal
$36,989 $361 $86,250
TOTAL IMPLEMENTED $3,891 $9,083 $1,525
53,928
kWh
$1,016
-
kW-mo/yr
- - - - $989 $361 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Fuel Oil #2 Savings Other Energy Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs